24-hour Community Hotline:1800 877 741
The existing SYD1 data centre on Harris Street, Ultimo

Construction underway · 2 stages in progress

DigiCo SYD1 Data Centre Expansion

390–422 Harris Street & 273 Pyrmont Street, Ultimo NSW 2007

This portal publishes construction progress, approved documents, environmental monitoring results and contact details for the project, as required by Condition C19 (Access to Information) of the development consent.

Delivered by SHAPE for DigiCo Infrastructure REIT

Key Project Facts
Consent SSD-69637456
Capital investment
$800 million
Construction jobs
~700
Additional IT load
52 MW
New levels
2
Height increase
~12 m
Programme
Oct 2026 – Dec 2028
Proponent
HDI SYD1 Property Holdings Limited
Builder
SHAPE Australia

Building Responsibly in Ultimo

DigiCo is expanding its existing SYD1 data centre at 400 Harris Street, Ultimo, making efficient use of established infrastructure to help meet Sydney’s growing need for digital connectivity. DigiCo and SHAPE are committed to delivering the project responsibly, maintaining open communication and working closely with the local community throughout construction.

This website has been created to keep residents, businesses and stakeholders informed about the project and the measures being taken to manage local impacts. Here you can access construction updates, environmental monitoring information and project resources, as well as contact our dedicated community team with any questions, feedback or concerns.

Our goal is to ensure the project is delivered with a strong focus on transparency, environmental performance and consideration for the surrounding community as we continue to support Sydney’s growing digital needs.

Standard Construction Hours

Monday to Friday
7:00am to 6:00pm
Saturday
8:00am to 1:00pm
Sunday and public holidays
No work, unless approved out-of-hours

Have Your Say

Concerned about construction activity, or have a question or suggestion? Let us know and the project team will respond.

Contact Us

Construction Progress

Where works are up to against the construction programme. Each stage is reported in detail in the community letters below.

Timeline

Forecast completion · December 2028

  1. Oct 2026 – Dec 2026Site establishmentCrane footings, hoarding and tower craneIn progress
  2. Oct 2026 – Apr 2028ConstructionData hall fit-out and rooftop worksIn progress
  3. Jul 2028 – Dec 2028Façade, landscaping and completionRe-cladding, hoarding removal and landscapingPlanned

Community Letters and Notices

Monthly updates, out-of-hours work notices, street impact notifications and letters, as delivered to letterboxes. Newest first.

The first community update will be published before works commence.